top of page
Search

Pex Tubing

  • Writer: Peter Armstrong
    Peter Armstrong
  • Nov 23, 2020
  • 1 min read

The radiant heat system installation continues. 5/16" pex tubing, secured with silicone sealant, has been installed in the pre-routed plywood panels throughout the second and attic floors.

The supply and return lines, fed through the floor to the rooms below, will be run to manifolds located throughout.

As you can see, we are working from the top floors down. Mechanical inspections for the first floor are scheduled for later this week. Insulation and Sheetrock to follow.

 
 
 

Comments


  • Facebook
  • Twitter
  • LinkedIn

©2019 by Owenoke Project. Proudly created with Wix.com

bottom of page